A contractor is required to undertake surveys, testing and investigations to support Pathway Stage 2 (Feasibility) of the Structures and Tunnels Investment Programme (STIP) 2 tunnels projects.

Bid for this and lost? There is a short window in which the decision can be questioned.

Awarded to

VVB Engineering Limited,£1.4mends (30 Mar 2018)

Details

What the buyer calls it
STIP 2 - Blackwall Southbound and Rotherhithe Tunnels Pathway Stage 2 (Feasibility Study)
How they are buying
Advertised, open to anyoneAny supplier could bid without being invited first.
Type
services
Work starts
11 Oct 2017
Work ends
30 Mar 2018

Who the buyer named

Mrs Omotunde Williams was the named contact on this notice.