What the buyer wrote

River regulation and flood control works. Floodgates. Flood-prevention works. In December 2013 the Suffolk coast suffered the most significant sea-surge generated flood event since 1953. Large parts of central Lowestoft were flooded by seawater, the majority of which came from overtopping of low parts of harbour quay walls in the outer harbour and Lake Lothing water areas. WDC has secured funding to manage the risk of an early repeat flooding event by use of temporary, fully removable flood barriers. WDC has secured funding to manage the risk of an early repeat flooding event by use of temporary fully, removable flood barriers. The alignment is designed to generally locate the barrier on…

Read all of it on Contracts Finder →

Bid for this and lost? There is a short window in which the decision can be questioned.

Awarded to

Geodesign Barriers Ltd£212.2kends (19 Sep 2021)

Details

What the buyer calls it
Supply of Fully Removable Temporary Flood Barriers
How they are buying
Advertised, open to anyoneAny supplier could bid without being invited first.
Type
goods
Work starts
19 Sep 2016
Work ends
19 Sep 2021
Kind of work
Construction

Who the buyer named

Samantha Cook was the named contact on this notice.