Trinity Academy Temporary Secondary School For Modular Temporary Accommodation
What the buyer wrote
The project requires a total of 6 temporary modular classroom units. One classroom unit will be required for 2 years for primary school use and will be located on the existing playground with an option to either provide a new/refurbished single classroom unit for hire or the relocation of an existing Portakabin twin classroom unit currently sited at Millpond Primary School in Bristol. The other 5 classroom units will be required from year 2 (2020), for one year and located adjacent to existing modular units on soft play area. Works to include connection of all services and remediation works following the end of the hire period. The proposed procurement is single stage D&B based on a sc…
Details
- What the buyer calls it
- Trinity Academy Temporary Secondary School For Modular Temporary Accommodation
- How they are buying
- Advertised, open to anyoneAny supplier could bid without being invited first.
- Type
- works
- Suitable for small firms
- The buyer says yes. What that is worth
- Work starts
- 14 Jul 2019
- Work ends
- 31 Aug 2021
- Kind of work
- New build construction, Building surveying and inspection
Who the buyer named
Tom Bryant was the named contact on this notice.