The works comprise the forming of a composite clay/earth bund using stockpiled material already present on site; the installation of drainage control structures; excavation of a flood attenuation basin; construction of onsite access routes and tie-in to existing highway; and the landscaping of the finished site.

Details

What the buyer calls it
Tull Way Flood Alleviation Scheme
How they are buying
Advertised, shortlist firstSuppliers applied to be considered, and the buyer picked who went on to bid.
Type
works
Work starts
30 Apr 2016
Work ends
31 Oct 2016

Who the buyer named

Contracts & Procurement Officer was the named contact on this notice.