What the buyer wrote
To design, manufacture, supply and install of the secondary lining moving gantries to the Main Tunnel and Greenwich Tunnel Civil Engineering and Tunnelling - The Main Contract works comprises the East Tunnelling section of Tideway Tunnel with works being undertaken at the main drive site Chambers Wharf, CHAWF, running East to Abbey Mills taking into shafts and tunnelling works at Deptford Church, DEPCS, King Edward Memorial Park Foreshore, KEMPF, Earl Pumping Station , EARPS, and Abbey Mills reception site.
Details
- What the buyer calls it
- Tunnel Secondary Lining Logistical Gantries
- How they are buying
- The buyer did not say
- Type
- works
- Suitable for small firms
- The buyer says yes. What that is worth
- Work starts
- 31 Mar 2021
- Work ends
- 22 May 2022
- Kind of work
- Roofing, windows and building fabric
Who the buyer named
Gary Peck was the named contact on this notice.