Upgrade of Electrical Infrastructure at Basildon Mental Health Unit
What the buyer wrote
Disconnect and remove existing main LV switchboard. Provide new LV switchboard with incoming feed from existing transformer and new standby generator. Re-serve all extisting sub-main services. Carry out alterations to existing HV transformer to provide the new LV supply to switchroom. Provide new standby generator dedictade to the Unit (this will serve all essential and non essential loads). Disconnect and remove existing standby generator. Carry out all construction, trenching, excavation work and builder work. The works will be let under a JCT minor works contract. During the course of the works 24 hour emergency response will need to be provided by the contractor in case of po…
Details
- What the buyer calls it
- Upgrade of Electrical Infrastructure at Basildon Mental Health Unit
- How they are buying
- The buyer did not say
- Type
- works
- Suitable for small firms
- The buyer says yes. What that is worth
- Work starts
- 1 Nov 2015
- Work ends
- 31 May 2016
Who the buyer named
Chris Dicketts was the named contact on this notice.