Due to an errant vehicle an area of impact damage has occurred to the West parapet wall of W78 Went Upper Bridge. The damaged areas require rebuilding works. The existing damaged stonework is located in the beck and requires removal. The works comprise: • Preliminaries. • Traffic Management. • Site Clearance. • Removal/disposal of stonework from beck to tip off-site. • Removal of stone reference D1 to tip off-site. • Laying of new stonework including provision of sandstone keys. This structure is listed. Additional information: All documents available from https://www.yortender.co.uk/ contract ref DN234771

Details

What the buyer calls it
W78 Went Upper Bridge - Masonry Repairs
How they are buying
Advertised, open to anyoneAny supplier could bid without being invited first.
Type
works
Suitable for small firms
The buyer says yes. What that is worth
Work starts
30 Jul 2017
Work ends
13 Aug 2017

Who the buyer named

Karen Towers was the named contact on this notice.

Ktowers@wakefield.gov.uk