Norwich City Council requires a single contractor for the site clearance, demolition and remediation works of an ex-works depot at a site in Norwich. The requirement is to clear the site and then demolish all above ground buildings and foundations including removing above and below ground fuel tanks and then remediate the area.

Bid for this and lost? There is a short window in which the decision can be questioned.

Awarded to

Armac Demolition Limited£1.5mends (14 Jul 2019)

Details

What the buyer calls it
9796 - Procurement of works - Mile Cross Demolition and Remediation - AWARD
How they are buying
Advertised, open to anyoneAny supplier could bid without being invited first.
Type
works
Work starts
14 Jan 2019
Work ends
14 Jul 2019

Who the buyer named

Richard Buckenham was the named contact on this notice.