GB-London: Feasibility Study into East Wing Switchboard Replacement
What the buyer wrote
The Contractor will need to carry out a detailed feasibility report for the replacement of the East Wing switchboard. •Establish locations for data logging to measure power consumption. •Undertake a detailed site survey to establish the load centres save and the address and destination of all associated LV cables. •Establish size of current conductors and assess load characteristics to confirm compliance with current BS7671. •Map all cable routs into and out of the switch room including containment. •Develop a changeover philosophy and plan that enables service to be maintained to minimise shutdowns. •Consider the phasing of the works and execution. …
Details
- What the buyer calls it
- GB-London: Feasibility Study into East Wing Switchboard Replacement
- How they are buying
- Advertised, open to anyoneAny supplier could bid without being invited first.
- Type
- works
- Work starts
- 30 Jun 2019
- Work ends
- 31 Oct 2019
- Kind of work
- Structural and civil engineering consultancy
Who the buyer named
Laura McAllister was the named contact on this notice.