The project involves the painting of the Wainwright Railway Bridge as part of its scheduled planned preventative maintenance regime.The works includes the surface preparation of the existing steel substrate and painted surfaces to receive a new paint system and colour scheme.

Bid for this and lost? There is a short window in which the decision can be questioned.

Awarded to

Coating Services£312.5kends (26 Feb 2021)

Details

What the buyer calls it
Maintenance Painting Wainwright Way Railway Bridge
How they are buying
Advertised, open to anyoneAny supplier could bid without being invited first.
Type
works
Work starts
1 Nov 2020
Work ends
26 Feb 2021

Who the buyer named

Peter Hughes was the named contact on this notice.