Modernisation Programme - Phase 2 - Cheshire Fire Authority
What the buyer wrote
***This is a Contract Award Notice*** Cheshire Fire Authority (CFA) - Modernisation Programme Phase 2. Following the success of building 4 new Fire Stations at Alsager, Lymm, Powey Lane and Penketh Cheshire Fire Authority (CFA) is looking to invest in the modernisation and re-modelling of 21 of their Fire Stations to bring them up to a standard closer to the new builds. Tarporley and Bollington fire stations have been contracted to Cruden Construction group (via the Procure North West Lite Framework) to drive progress in the programme, this leaves 19 fire stations over the 5 year programme. The Stations are located across the Cheshire Fire and Rescue Service area and vary in size, form of…
Bid for this and lost? There is a short window in which the decision can be questioned.
Awarded to
Details
- What the buyer calls it
- Modernisation Programme - Phase 2 - Cheshire Fire Authority
- How they are buying
- The buyer did not say
- Type
- works
- Suitable for small firms
- The buyer says yes. What that is worth
- Work starts
- 13 Jun 2019
- Work ends
- 31 Mar 2025
Who the buyer named
Helen Elliott was the named contact on this notice.