What the buyer wrote
The implementation of Smart Motorways requires a detailed understanding of the existing assets prior to the assessment, design and construction of appropriate solutions. It requires surveys of the existing asset in order to provide sufficient asset as-built and condition information and to inform the design team of any necessary infrastructure interventions required for the delivery of the Smart Motorway schemes. This includes pavements, drainage and topographical surveys. The schemes included in this package order are M1 J35a-J39, M1 J19-J23a and M42 Birmingham Box Phase 4 J0-J3 & M5 J4A-J4
Bid for this and lost? There is a short window in which the decision can be questioned.
Awarded to
Details
- What the buyer calls it
- TMTii 46- SMP Tranche 6 Asset Data Capture
- How they are buying
- The buyer did not say
- Type
- services
- Work starts
- 10 Jun 2018
- Work ends
- 14 Dec 2018
Who the buyer named