Under Track Crossing of Utilities - Old Oak Common (S4) Station - HS2
What the buyer wrote
Under Track Crossing of Utilities 8 Nr pipejacks under the GWML and North Depot railway to carry diverted utilities The UTX will be formed of 8 No. 1.2m internal diameter precast concrete pipes jacked through the ground below the GWML and North Pole (IEP) railway lines. Seven of the bores are to be constructed from a temporary steel sheet piled launch pit located adjacent to OOCL within the decommissioned Hex depot. They will be jacked approximately 175m to a reception pit located within the Wormwood Scrubs common land just south of the boundary to the IEP depot. The eighth bore, which is nearest to Old Oak Common Lane, is to be driven from reception pit…
Bid for this and lost? There is a short window in which the decision can be questioned.
Awarded to
Details
- What the buyer calls it
- Under Track Crossing of Utilities - Old Oak Common (S4) Station - HS2
- How they are buying
- The buyer did not say
- Type
- works
- Work starts
- 16 Mar 2020
- Work ends
- 7 Dec 2020
Who the buyer named