Skip to the main content
The Crier

Royal Docks Capacity Enhancement

Your saved contracts

What the buyer wrote

NEC Engineering and Construction Contract Option A: Priced Contract with Activity Schedule (Third edition June 2005 with amendments June 2006 and April 2013) together with Schedule 1 Amendments to Conditions of Contract and the Schedule 1 Z Clauses.

Bid for this and lost? There is a short window in which the decision can be questioned.

Awarded to

Dyer & Butler Ltd£8.2mends (17 Jan 2018)

Details

What the buyer calls it
Royal Docks Capacity Enhancement
How they are buying
Advertised, shortlist firstSuppliers applied to be considered, and the buyer picked who went on to bid.
Type
works
Work starts
30 May 2017
Work ends
17 Jan 2018
Kind of work
Construction

Who the buyer named

The buyer published a contact address on this notice.

BSFAribaAdministration@tfl.gov.uk